Hi All,
To create a project I have created standard WBS template and created Standard network with few activities.The activities are tagged to WBS elements created in std.WBS template.
We are following assembly processing to create a project through contract.I have assigned the standard templates to specific material in CN08 and then creating contract.While saving contract project is getting created.
My problem is few wbs in standard wbs template to which there is no activity assignment in network are not coming in project structure whereas when i am creating a project manually in cj20n copying the standard template all levels are coming properly.
Is there any setting we need to do to capture those wbs to which there is no activity assignment or it is a standard behavior??
Regards,
Blessedgirl