Hi
Actually we assign the reduction strategy in OPL8 with respect to Order Type.
My Question is :
1. We already defined values to Reduction level in OPJS.
For Example : L1 - 10% ; L2 - 20% ; L3 - 30%; L4 - 40% ; L5 - 50% and L6 - 60%.
In this case, If we assign the "Max reduction level" in OPU3 / OPU5 as Upto Level 3 then the SIX INPUT BOXES i.e., "% in reduction in Float" should be updated as "10" , "20" , "30" , "BLANK" , "BLANK" & "BLANK".
But it is not getting updated and we have to enter it manually again. Why this happens ?
Note : I assumed "% in reduction in Float" (OPU3) = "Reduction Level" (OPJS)
Correct if my assumption is Wrong.
Thanks With Regards,
Dinesh Kumar V.