Hello,
The GR processing time is available on material master, and on the SA. However, MRP is taking into consideration the GR processing time on the material master, not the SA ( assumption was the lowest level would be taken into consideration).
Is anyone aware of a setting to allow the GR processing time used on the SA instead of the material master? I know for planned delivery you have the SA/inforecord setting in configuration, but don't see the same for GR processing time.