Hi Pavan,
Okay, so let's say we have:
- main cost component structure Z1: 10-Energy
- aux cost component structure Z2: 11-Electricity; 12-Water
Now, we all know that if the Energy is the activity type related, so it will use the secondary cost element. While for the Electricity & Water, which is primary cost element and will be mapped in the OKES splitting to the energy.
During the order settlement, the variance breakdown to COPA, we can only see the variance of energy.
Now, the requirement is, during order settlement, the variance need to be split for electricity and water. --> this is the question that trigger this discussion. Do you think this is possible?
Thanks & Regards,
Erwin